Last issue covered the road from PoC to production, and the conclusion was: when a fleet scales, the ledger breaks before the network does. Once the ledger is built, credentials are governed, and bulk import works, the project moves into its next stage — the supplier hands you several hundred or several thousand devices. How do you take delivery?

This question does not exist in the pilot phase: twenty devices, unbox, power on, join — done. At production scale, an inspection process that does not scale up turns "a bit of trouble" into a bad batch sitting in your warehouse — devices lying on a shelf for three months, installed on site, only then failing to join. By then the supplier's warranty clock is running, the project schedule is running, and the installer's travel budget is running. Stopping problems before goods leave the warehouse is the highest-leverage gate in the whole delivery chain.

This issue lays out factory acceptance in full: checking the shipping paperwork, what to inspect at unboxing, how to sample, how gateway acceptance differs from end-device acceptance, how to handle failed batches, and how acceptance results connect to the ledger from last issue.

1. Acceptance Screens Money, Not Just Devices

Run the numbers first. Suppose one thousand devices ship to forty installation sites across three cities, and before dispatch you discover that one batch's AppKey labels do not match the provisioned keys:

The math defines the division of labor: the supplier's inspection report answers "the devices were good when they left the factory"; your acceptance answers "they are still good when they reach you, and they match the ledger". Between those two points lie transport, warehousing, and repacking — any of which can introduce new problems: scuffed labels, electrostatic damage, wrong batch shipped. Acceptance is not distrust of the supplier; it nails the responsibility boundary down to the last screw.

Put the acceptance criteria in the purchase contract, not in an email thread. At minimum the contract must state three things: the acceptance standard (which specification it references), the sampling plan (what proportion, what pass line), and the remedy for failed batches (rejection, replacement, or rework — and who bears the cost).

2. The Three Shipping Documents: Missing One Pauses Acceptance

Before opening a single box, check the paperwork. Last issue introduced the batch manifest (each device's EUI, keys, hardware version, firmware version) — it is the source of the ledger import and the backbone of acceptance verification. A proper delivery includes at least three documents:

If any of the three is missing, pause acceptance and record it in writing. This is not pedantry: a batch without a manifest means the ledger has no source; a batch without an inspection report means the quality commitment has no anchor.

3. Unboxing Verification in Five Steps

Once the documents check out, open the boxes. Unboxing verification aims to filter out every problem that is visible without instruments, in five steps:

Step one, quantity and batch reconciliation. Physical count against the packing list; in-carton batch marks against the contract batch. Mixed or mis-shipped batches surface here — the cheapest possible discovery point.

Step two, appearance and packaging. Cracked enclosures, bent pins, bulging batteries (for battery-powered end devices), displaced seals (for IP65/IP67 devices). Electrostatic and drop damage may not be visible, so devices from damaged cartons get flagged and pushed into the sampling pool.

Step three, label verification. The most underestimated step with the heaviest consequences. Confirm device by device that the DevEUI on the label is legible and the barcode or QR code scans — last issue established that the ledger tracks assets, not device names, and the anchor between ledger and physical unit is exactly this label. Faded labels, missing labels, duplicate EUIs (two devices with the same DevEUI) are all nonconforming. Duplicates almost never appear in a pilot; at ten-thousand-unit volumes they are a real production-line accident, and labels are the only place you will catch them — a join test may even succeed, because duplicated DevEUIs joining separately do not always expose the conflict immediately.

Step four, batch-consistency spot check. Pull random entries from the manifest and compare them against physical labels. This step verifies that the manifest and the devices are the same batch — transcribed manifests, shifted rows, and batches padded from other lots all surface through spot checks.

Step five, firmware version check. Compare the manifest's firmware version against the actual device version. A mismatch has two remedies: have the supplier update to the target version on the spot, or treat the batch as mis-versioned under the contract. Last issue noted that whether a 1.0.x device can ever join a multicast session depends on whether GenAppKey was provisioned on the production line — that decision hardens the moment the device ships. Finding wrong provisioning at acceptance is the last cheap chance to fix it.

4. How to Sample: Proportion, Items, Pass Line

Full inspection is unrealistic at production scale — a join test per device means a thousand devices cost a day of test-bench time plus a day of ledger time. The engineering answer is sampling per GB/T 2828.1 (ISO 2859 equivalent, sampling procedures for inspection by attributes), with sample size set by lot size and general inspection level II, and AQL agreed in the contract — strict for credential-critical items, relaxed for cosmetic ones.

Sampling items fall into three layers, ordered by "can it join, and is it accurate once it does":

Write the pass line into the contract, for example: credential layer (join success) with zero failures in sample — one failure fails the whole batch; appearance and function judged by AQL. The principle: credential defects get no statistical mercy — a wrong key is not "normal process variation"; it is a production-line configuration error, and one wrong unit usually means a wrong batch.

5. The Gateway-Specific Items

A gateway is not "a bigger end device"; several acceptance items belong to gateways alone:

Gateway counts are usually far smaller than end-device counts — a few to a few dozen per coverage area — so sampling can scale up to full inspection. A gateway is the convergence point for every device under it; one bad gateway affects everything it covers.

6. Three Remedies for a Failed Batch

When sampling fails, the remedy is pre-agreed in the contract — no on-the-spot bargaining:

All three paths share one prerequisite: batch quarantine. The moment a failure is ruled, the whole batch moves to a segregated storage zone and the ledger marks it disabled, so nothing leaks to an installation site. Last issue's ledger lifecycle states — in stock, in use, repair, retired — gain one more state here: "pending inspection". Every delivered device sits in pending inspection until acceptance completes, then moves to in stock.

7. After Acceptance: Stock-In Is Ledger-In

The final step of acceptance lands its results into the ledger, closing the loop with last issue:

The delivery chain now closes end to end: the production line provisions credentials (first half of last issue) → the manifest ships with the batch → factory acceptance verifies → accepted stock enters the ledger → gated rollout brings it online. Next issue covers the last link in the chain: once the devices are mounted, how to build the operations SOP.

8. The Acceptance Checklist

Everything above compresses into one executable page — tick each item on acceptance day:

  1. Three shipping documents complete (packing list / batch manifest / factory inspection report)
  2. Physical count matches the packing list; no mixed batches
  3. Appearance inspection done; damaged cartons flagged separately
  4. Every label legible and scannable; no duplicate EUIs
  5. Manifest spot check matches physical labels
  6. Firmware versions match the manifest (including multicast provisioning, where contracted)
  7. Sampling plan and AQL executed per contract
  8. Sampled units pass OTAA join tests; credential layer with zero failures
  9. RF baselines recorded; no intra-batch outliers
  10. Gateway backhaul links, platform registration, and update rehearsal all completed
  11. Failed batches quarantined and dispositioned in writing
  12. Accepted batches imported into the ledger; online spot check passed
  13. Spares and retained samples carved out; shipping documents archived

None of these items needs advanced tooling. They need exactly two things: acceptance criteria written into the contract, and the ledger system from last issue. Acceptance is not distrust of your supplier — it turns "good at the factory, good on arrival, ledger matching reality" into a provable fact. The larger the project, the cheaper this gate.